In 2012 Heinen & Hopman was awarded the contract to upgrade the HVAC systems of an FPSO which was originally built in 1983. The FPSO was sold to a new owner in 2012, but had to undergo an extensive refit before being deployed in the oil fields.
A Floating Production, Storage and Offloading unit is a floating vessel used by the offshore oil and gas industry for the production and processing of hydrocarbons, and for the storage of oil. These vessels are particularly effective in remote or deep water locations, where seabed pipelines are not cost effective. As the costs for laying these expensive pipelines are eliminated, FPSOs are an economically attractive solution for smaller oil fields, which can be exhausted in a few years.
The contract awarded to Heinen & Hopman included the following items:
The refit was a challenging project in terms of engineering, planning and logistics. It was a multi-disciplinary (heating, ventilation, air conditioning, refrigeration and sanitary hot water systems) project that had to be completed in a tight project schedule. Moreover, the work had to be done at different project locations. The following systems were provided by Heinen & Hopman:
2x 50% DX-cooling system
1x Air Handling Unit
1 lot Supply ornaments with electrical re-heating
1 lot Extraction systems serving various rooms (e.g. Galley, Hospitals, Recreation rooms, etc.)
1x Central HVAC control & monitoring system, including redundant PLC
1x Sanitary hot water system for a POB of 96 persons
1x Temporary Refuge (TR) filter-/pressurization system.
1x 2x 100% refrigeration compressor skid
4x Evaporator for cooler/freezer rooms
1x Central HVAC control & monitoring system
1x Engine Room ventilation system with active pressure control
1x Air Compressors air supply system
1x Chilled water cooling system serving various areas (e.g. Integrated Equipment Room, Server Rooms)
2x Ventilation system for Fire Pump Rooms including active power ventilation
2x 100% ventilation/pressurization system
1 lot Active pressure control for individual rooms
3x AC-unit, with 2x50% fan section - total cooling capacity of 240kW
3x Air Cooled Condensing Unit for AC-unit - AISI-316, ATEX Zone II
2x 100% ventilation/pressurization system
1 lot Active pressure control for individual rooms
1x AC-unit with 2x100% fan section - total heating capacity of 80kW
1x Air Cooled AC-unit serving Instrument Room - AISI-316, ATEX Zone II
Upgrading the HVAC system also provides you with the benefits of the latest technology. New equipment operates much more efficiently compared to older systems and consequently operating costs can be strongly reduced.